Worship Center 

REFRESH

UPDATES

Latest Updates 

Week 13

September 6-12th

We’re in the final stretch! All of the pews have now been installed, and final cleanup, technology work, and preparations are underway as we get the Worship Center ready for our return on Sunday, September 13th!

Work has also begun outside the Worship Center! We broke ground on the outdoor improvement project, which will level the area in front of the Worship Center and create a more usable space.

After months of progress, we’re excited to see everything coming together and can’t wait to welcome everyone back to the Worship Center this Sunday!

This Week’s Progress

Previous Updates

Demolition and preparation work began in the Worship Center on June 15, marking the start of the first phase of the Worship Center Refresh. Crews made great progress as work got underway.

  • All Equipment Moved
  • Dumpster Delivered
  • Pews Removed 
  • Carpet Removed
  • Center Big Screen Removed

Demolition continued this week as crews prepared the Worship Center for the next phase of construction. Significant progress was made throughout the space, and the transformation is becoming more visible each week.

  • Riser demolition
  • Electrical demolition and rework
  • Drywall installation, taping, and sanding behind the risers and around the large screen opening
  • New concrete step work began

Crews completed the new concrete steps and began  painting, marking another visible step forward in the Worship Center Refresh.

  • Continued work behind the risers and around the large screen opening
  • Completed concrete work for new steps 
  • Prep work for painting
  • Painting began

Painting has been completed, and carpet installation is officially underway. With these major milestones complete, the Worship Center is beginning to take on its refreshed look as work continues to move forward.

  • Painting completed
  • Carpet installation began
  • Back office furniture removed

Carpet installation continued throughout the Worship Center, with crews completing work on the platform. Preparation also continued for carpet installation in the Music Suite, offices, and the stairs leading to the baptistry as the Worship Center Refresh moved steadily toward completion.

Carpet installation continued throughout the Worship Center, with carpeting completed on the platform, stage stairs, and the stairs leading to the baptistry. Crews also prepared to move into the Music Suite and offices as the Worship Center Refresh continued to make steady progress.

Carpet installation was completed in the Music Suite and offices. With carpeting finished, work shifted to technology installation, including the new LED screen and A/V equipment. 

Installation of the new LED screen was completed, baseboards were reinstalled throughout the Worship Center, and the back offices in the Music Suite received fresh paint. Additional A/V and technology upgrades continued as the refresh moved closer to completion.

All electrical and technology work related to the new LED screen and lighting upgrades was completed.

We also announced that we are planning to return to the Worship Center on Sunday, September 13th! 

 

Week 11 brought several exciting finishing touches to the Worship Center! The chairs were reupholstered with their new material, the risers were installed, and a newly painted cross was hung in the baptistry.

Week 12 brought more finishing work throughout the Worship Center! Work in the offices and Music Suite was completed, doors and trim received fresh paint, and cleanup continued throughout the space.

Installation of the pews also began, bringing another major piece of the Worship Center back into place as we moved closer to our return on Sunday, September 13th!